LUDHIANA: As the Delhi-Katra Expressway is expected to decrease the distance between Ludhiana and other cities of North India, including Delhi and Jammu, a recent status report from NHAI suggests that of the two parts of the highway in the district, one is expected to be completed by the end of September and the second in March next year.
Meanwhile, according to an NHAI official, the govt has set a target of the end of June for the completion of the road from Delhi to near Bogiwal before it enters Ludhiana district.
According to the recent status report, of the 35.09 kilometres road length of Package Eight, of which around 22 kilometres are in Ludhiana district and the remaining is in Malerkotla district, 31.08% physical progress and…